The restoration projects which the Berks County Conservancy will be using some of the native seed the Berks Native seedbank volunteers have helped collect, sort and clean.
Spring 2009
Riparian projects:
At Red Bridge, in the Gring's Mill Recreation area, an area approximately 20 x 300' in size,this is a disturbed area not fully covered by earlier restoration efforts. Planting time not yet determined.
At Stonecliffe Park along the Tulpehocken creek an approximately 20 x 300' area. Top soil has been newly spread in the area. Planting time not yet determined.
At Angelica Park an area needs help. It has been sprayed to control invasives. Size? Planting time early spring before normal plants growth begins.
Photos above of Boltonia Asteroides (Aster-like Boltonia) and Verbena hastata (Blue Vervain) are by Mike Slater
Hillside at Alvernia College:
Saucony Creek Area Moist Meadow:
- A hill side area 60 x 200' in extent has been distrubed by mechanical activity and then regraded. There will be scattered trees planted with native meadow plants to be seeded in between. Planting probably in late February or early March 2009.
- An area of 50' by 200' wwhich has been spraed to control invasives will be overseeded with native meadow grasses and wildflowers. Planting probably in late February or early March 2009.
Kutztown Area Well Buffers:
- Several 300' diameter circular vegetation buffers around wells in a moist meadow. The total area to be restored is about 4 acres. Thie area will be planted with scattered trees and shrubs with native meadow grass and wild flower seed planted in between. The area has been farmed for corn up until the fall of 2008.
This area is also may be a good place to put some of the potted plants we are propagating in pots in this first planting year at the site. (Planting plants into an established meadow is difficult due to root competition with the pre-existing plants)
Fall 2009
Riparian areas which will be exposed due to Dam removal projects
Witman Dam near Oley, Planting will probably in November 2009 or later.
Bushong Dam on the Tulpehocken Creek at the confluence with the Schuylkill River. Planting will probably be in November 2009 or later.
Photos above of Boltonia Asteroides (Aster-like Boltonia) and Verbena hastata (Blue Vervain) are by Mike Slater
_________________________________________________
Update:
The list of seed from the given to the Berks County Conservancy for planting in the above areas is on the 2009 seed list page.
No comments: